30th June, 2018
TOWER A
TOWER B
TOWER CAluminum Window fitting in progress
TOWER DExternal Painting in progress
TOWER ERCC: 22nd floor slab work completed
TOWER FRCC: 22nd floor slab work is in progress
TOWER GPour 1 & Lift area work is in progress
TOWER G Extended BasementStitch slab work is in progress
Club HouseExternal painting work is in progress
Festival PavilionMS Fabrication & External painting work is in progress
Court Yard & Town HallInternal & External finishing work is in progress
Basement AreaParking painting & Housekeeping is in progress